A 42-minute route contains 24 minutes of walking, 8 minutes of searching, 7 minutes of picking, and 3 minutes of waiting. The first test should reduce walking or search—not ask the picker to move faster.
Signs to confirm on the floor
- Lines per labor-hour misses plan
- Workers finish routes at very different rates
- Rush orders create repeated route interruption
- Supervisors blame individual effort without time composition
Check more than one possible cause
The first explanation may sound right and still be wrong. Use the measurements in the next section to separate these possibilities.
Poor slotting or route geometry
High search time and unclear locations
Order way to organize the work repeats travel
Replenishment or problems interrupt normal work
Later release throttles visible completion
Numbers that can change the decision
Choose a fix only after the facts point to it
A practical seven-day starting plan
- 01
Observe 30 consecutive routes without coaching
- 02
Time travel, search, confirm, handle, wait, and problem separately
- 03
Upload four realistic weeks to the order analyzer
- 04
Model the top two ways to organize the work
- 05
Test one bounded change with frozen definitions